Vancouver multiplex permits: how many, how big, and how long they take

About 340 Vancouver multiplex projects have building permits, with roughly 1,200 homes. How big they are, where they are, and how long permits take.

Rules and permits 5 min read By T-City Developments

Original analysis of City of Vancouver open data

A finished three-storey multi-unit home with grey and cedar cladding
Contents 10 sections
  1. What a multiplex is, in plain words
  2. What we found
  3. From application to permit
  4. Planned projects versus permitted ones
  5. Why permits take longer than for a duplex
  6. Rules under review
  7. What it means if you own a lot
  8. What we expect in 2027
  9. Questions
  10. Sources

Vancouver has issued building permits for about 340 multiplex projects since the first one on June 4, 2024, holding roughly 1,200 new homes. More than 600 projects had been submitted by May 2026, so a little over half have made it to a permit. Most are three or four homes split between a front and a back building. A permit took a median of 192 days in 2026, longer than a duplex or a laneway house.

What a multiplex is, in plain words

Since fall 2023, most single-family lots in Vancouver have been zoned R1-1. That zone lets you build a multiplex: three to six homes you can sell separately. Or you can build up to eight if every home is a rental, and the owner can live in one. The total floor area can be up to the lot’s size, a floor space ratio of 1.00. How many homes you can build depends on the lot:

Vancouver R1-1 multiplex: homes allowed by lot size
HomesSmallest lot allowedNarrowest frontage allowed
3 or 4306 m² (3,294 sq ft)10.0 m (33 ft)
5464 m² (4,994 sq ft)13.4 m (44 ft)
6, or up to 8 rentals557 m² (5,996 sq ft)15.1 m (50 ft)

The front building can be three storeys and 11.5 m tall. A back building is limited to two storeys and 8.5 m.

How we build multiplexes

What we found

We read every new-building permit issued by the City of Vancouver up to October 2, 2026 that mentions a multiplex: 594 permits. Most projects get two permits, one for the front building and one for the back, so we grouped them by lot.

  • 339

    Multiplex projects have building permits: 31 in 2024, 181 in 2025 and 127 so far in 2026.

  • ~1,200

    They hold roughly 1,200 homes. We counted 1,069 homes in the 301 projects whose permits spell out the number.

  • 77%

    Three and four homes are the norm. Of the projects with three or more homes listed, 37% have three, 40% have four, 9% have five and 14% have six or more.

  • 78%

    Include a three-storey building.

  • 0.94

    Parking is light: about 0.94 spaces per home where the permit lists parking.

  • 192 days

    Permits are getting slower: a median of 122 days in 2024, 171 in 2025 and 192 in 2026. That compares with 130 days for duplexes and 99 for laneway houses this year.

  • 54

    The east side leads. Hastings-Sunrise has the most projects (54), then Kensington-Cedar Cottage (36), Dunbar-Southlands (27), Kerrisdale (26), Victoria-Fraserview and Renfrew-Collingwood (25 each).

About 340 multiplex projects have reached a permit since mid-2024 Multiplex projects by the quarter their first building permit was issued, Q2 2024 to Q3 2026
  • Busiest quarters
  1. Q2 2024 : 1
  2. Q3 2024 : 8
  3. Q4 2024 : 22
  4. Q1 2025 : 30
  5. Q2 2025 : 41
  6. Q3 2025 : 52
  7. Q4 2025 : 58
  8. Q1 2026 : 38
  9. Q2 2026 : 28
  10. Q3 2026 : 58

T-City analysis of City of Vancouver open data: 594 new-building permits mentioning a multiplex, grouped into projects by lot, to October 2, 2026

From application to permit

The City and outside trackers have published application counts along the way. Put next to our permit count, they show the program growing fast, then settling down:

Vancouver multiplex applications and permits over time
DateMultiplex projectsSource
March 7, 202449 applicationsMore Housing tracker
March 31, 2025About 370 applications, about 1,500 homesCity of Vancouver memo to Council
May 2026More than 600 submitted, more than 280 approvedCity staff, reported with Council Motion 9
October 2, 2026About 339 with building permits, roughly 1,200 homesT-City analysis of City permit data

Applications ran at about 320 in the year to March 2025, then about 230 in the 14 months after. Interest is still strong, but the first rush is over.

Planned projects versus permitted ones

The City’s 2025 count of applications and our count of permits show a similar mix, with one difference: six-home projects.

Homes per multiplex project: applications against permits
Homes per projectShare of applications, to March 2025 (City)Share of permitted projects (T-City)
329%37%
445%40%
59%9%
6 or more18%14%

Our read is that bigger projects take longer to reach a permit, and some get scaled back along the way. Six homes need a 50 ft lot and usually a more complex building. And on large lots west of Ontario Street, strata projects also have to give 5% of their floor area to social housing, or pay cash instead.

Why permits take longer than for a duplex

A multiplex is two buildings, often with a three-storey front. It fits more homes under one floor-area limit. And it has family-size rules: a strata fourplex needs at least two homes with two or more bedrooms. Each of those adds review time. The City’s 2025 memo also said a large share of multiplex applications were courtyard designs (70%), which usually means two buildings and more site planning. For the duplex side of the comparison, see how long it takes to build a duplex.

Rules under review

On May 20, 2026, a Council committee approved Motion 9, asking staff to review the multiplex rules after early experience. The review covers building size and massing, setbacks, tree canopy and neighbours’ privacy, and lines the rules up with the Province’s Bill 25. Staff were told to keep things predictable for applicants. No report-back date was set.

What it means if you own a lot

  1. Measure your frontage first. 10 m gets you three or four homes. 15.1 m gets you six. A lot feasibility study confirms it before you pay for design.
  2. Plan for about six months of permitting in 2026, not three.
  3. Check which side of Ontario Street you’re on if your lot is 623 m² or bigger and 17.1 m wide or more, because of the social housing requirement.
  4. Decide strata or rental early. Rental allows up to eight homes, but you can’t sell them separately. If you’re selling, budget for strata titling.
  5. Consider applying before the review lands, if your design depends on today’s massing rules.

Our duplex vs triplex vs multiplex guide compares the options lot by lot.

What we expect in 2027

  1. About 150 to 180 multiplex projects permitted, close to the 2025 to 2026 pace, as the slower flow of applications works through.
  2. Permit times stay near six months until the City finishes its review.
  3. Rule changes on massing and trees from the Motion 9 review, most likely late in 2027. Projects already in the system should keep today’s rules.
  4. Six-home projects stay rare, below one in five.

Sources

Every outside figure traces to one of these pages, all opened on October 14, 2026. T-City’s own analysis uses the City of Vancouver open datasets. Rates and fee schedules change, so we recheck them for your lot during feasibility.

Common Questions

Frequently Asked Questions

How many multiplexes has Vancouver approved?

About 339 projects had building permits by October 2, 2026, with roughly 1,200 homes. City staff reported more than 600 submitted by May 2026.

How long does a multiplex permit take in Vancouver?

A median of 192 days in 2026, based on City permit data.

How many homes can I build on my lot?

Three or four on a lot at least 10 m wide and 306 m². Five from 13.4 m and 464 m². Six, or up to eight rentals, from 15.1 m and 557 m².

Where are multiplexes being built?

Mostly on the east side. Hastings-Sunrise has the most permitted projects, followed by Kensington-Cedar Cottage.

Are multiplex rules changing?

A Council committee asked staff in May 2026 to review massing, setbacks and tree rules. Changes haven’t been decided yet.