How much does it cost to build a multiplex in Vancouver?

A Vancouver fourplex costs about $1.7M to $2.5M to build before land. What 187 City permits show per home, the $130,500 in charges, and how to plan the budget.

Costs and financing 5 min read By T-City Developments

Original analysis of City of Vancouver open data

A finished three-storey multi-unit home with grey and cedar cladding
Contents 12 sections
  1. What we found
  2. What is a multiplex
  3. What does the building itself cost
  4. What a fourplex costs, line by line
  5. Where do the charges go
  6. What makes a multiplex cost more or less
  7. How do you pay for it
  8. What about selling the homes
  9. How long does it take
  10. What we expect in 2027
  11. Questions
  12. Sources

Plan on about $1.7 million to $2.5 million to build a fourplex on a standard 33 ft Vancouver lot, before you count the land. That works out to about $430,000 to $630,000 per home. The building is the biggest part: on City permits, each multiplex home has a median value of $421,000. City and regional charges add about $130,500 more.

What we found

We read every multiplex building permit Vancouver issued up to October 2, 2026. Here’s what they show:

  • $421,000

    Is the median construction value per multiplex home on Vancouver permits. The middle half run from $350,000 to $500,000.

  • $900,000

    Is the median value written on the permit for a two-home multiplex building. A one-home back building is $365,000.

  • $130,500

    In city and regional charges on a Vancouver fourplex on a 33 ft lot, at July 2026 rates.

  • 70%

    Of a Vancouver fourplex’s charges go to Metro Vancouver and TransLink. They charge for every home.

  • +$23,000

    More in regional charges for the same fourplex when Metro Vancouver’s new rates start on January 1, 2027.

What is a multiplex?

A multiplex is three to six homes on one lot, and in Vancouver you can sell each home on its own. Or you can keep up to eight homes as rentals instead. Most are split into a front building and a back building, with a courtyard between them. See how many multiplexes Vancouver has approved.

A standard 33 by 122 ft lot can hold three or four homes. It gets 1.00 FSR, which means the floor area can match the lot area: about 4,026 sq ft in total.

What does the building itself cost?

Every permit lists a construction value, which is the owner’s or builder’s estimate when they apply. For a multiplex, the City usually issues one permit for each building, so we divided each building’s value by the number of homes in it.

The median is $421,000 per home. That’s close to a duplex half, at $450,000. But multiplex homes are usually smaller, so each square foot costs a bit more to build.

A multiplex home costs about as much to build as a duplex half Median construction value declared per home on Vancouver permits: houses and laneway houses in 2026, duplex halves in 2025–26, multiplex homes since 2024
  • Multiplex home
  1. New house : $990K
  2. Duplex half : $450K
  3. Multiplex home : $421K
  4. Laneway house : $350K

T-City analysis of City of Vancouver open data: issued building permits, January 2017 to October 2, 2026. Multiplex: 187 permits for a single front or back building, divided by the homes in that building

Chart: T-City Developments · tcitydevelopments.com

Treat permit values as a floor, not a quote. Nobody rounds them up, because the permit fee is based on them. For new houses, the finished building was later assessed at 1.65 times its permit value. See what a house costs to build.

Rules checked: September 2026. Sources: City of Vancouver Open Data: Issued building permits (January 2017 to October 2, 2026). Bylaws change, so we confirm every figure against your specific lot during feasibility.

What a fourplex costs, line by line

Here’s a fourplex on a 33 by 122 ft lot (374 m²), built to the full 1.00 FSR:

Cost to build a fourplex on a 33 × 122 ft Vancouver lot, before land
CostAmountWhere the number comes from
Building$1.4 million to $2.0 millionFour homes at $350,000 to $500,000, the middle half of multiplex permits since 2024. Probably low
City development leviesabout $30,300$81.13 per m² of floor area, City DCL bulletin
Amenity Cost Chargeabout $9,300$24.97 per m², since September 30, 2026
Metro Vancouver and TransLinkabout $90,800$22,711 per home at townhouse rates, from July 24, 2026
Tearing down the old house$30,000 to $50,000Our demolition cost analysis
Design, engineering, survey, energy advisor, warranty, insurance, legal and strata$110,000 to $240,000Planning allowance: 8% to 12% of building
Construction loan interest$60,000 to $90,000Planning allowance: about 18 months of draws at 6%
Total before land and permit feesabout $1.7 million to $2.5 million

That’s about $430,000 to $630,000 per home. Permit fees come on top, and the City sets them from the value of the work.

Where do the charges go?

A fourplex pays about $130,500 in charges, and most of it doesn’t go to the City. Metro Vancouver and TransLink charge for every home on the lot. So a duplex pays their charges twice, while a fourplex pays them four times.

A Vancouver fourplex pays about $130,500 in development charges Charges on a four-home multiplex on a 33 × 122 ft lot at 1.00 FSR, at rates in force from July 24, 2026
  • Regional: Metro Vancouver and TransLink
  • City of Vancouver
  1. Metro Vancouver water : $39,356
  2. Metro Vancouver sewerage : $38,372
  3. City-wide DCLs : $30,343
  4. TransLink : $11,348
  5. Amenity Cost Charge : $9,339
  6. Metro Vancouver parkland : $1,768

T-City calculation: 374 m² of floor area, four homes at Metro Vancouver and TransLink townhouse rates. Sources: City of Vancouver DCL and ACC bulletins, Metro Vancouver and TransLink rate tables

Chart: T-City Developments · tcitydevelopments.com

For the same lot, a duplex pays about $70,800, plus about $6,500 in amenity charges. See the duplex charges, line by line.

Rules checked: September 2026. Sources: City of Vancouver Development Cost Levies Bulletin (amended August 25, 2026), City of Vancouver Amenity Cost Charges Bulletin, Metro Vancouver: Liquid waste development cost charges (rates from July 24, 2026 and January 1, 2027), Metro Vancouver: Regional water development cost charge, Metro Vancouver: Regional parkland acquisition development cost charge, TransLink: Development cost charges (2026 rates). Bylaws change, so we confirm every figure against your specific lot during feasibility.

What makes a multiplex cost more or less?

  • Number of homes. Each home needs a kitchen, bathrooms, its own meter and fire walls. Three bigger homes can cost less than four smaller ones
  • Stacked or side by side. Homes stacked on top of each other need extra fire and sound floors, and more stairs
  • Basement. Digging, shoring and waterproofing add a lot. A basement still counts as floor area
  • Parking. Vancouver multiplexes average less than one space per home. Fewer spaces leave more room for homes
  • Services. Four homes may need a bigger water line, sewer connection and electrical service
  • Finishes. The part you control most. Simple finishes repeated four times save real money

How do you pay for it?

Most owners use a construction loan, where the bank pays out in stages as the building goes up. Your lot usually counts as your down payment.

If you plan to rent all the homes, two programs can help. A building with at least four rental homes may get all its GST back through the federal rental rebate. CMHC’s MLI Select loan program starts at five rental homes. Check both with your accountant and lender before you design.

What about selling the homes?

To sell each home, you need a strata plan that gives each home its own title. With four homes or fewer, you don’t need a disclosure statement. With five or more, you do, and that adds legal work and time before you can sell.

That’s one reason many owners stop at four homes. See duplex vs triplex vs multiplex to compare the options on one lot.

How long does it take?

A multiplex permit took a median of 192 days in 2026, which is longer than a duplex at 130 days. See every step from lot check to keys. Building takes longer than a duplex too, because there are usually two buildings and more homes to finish.

What we expect in 2027

  1. Higher regional charges. Metro Vancouver’s rates go up on January 1, 2027. For a fourplex, that’s about $23,000 more. City levies rise 3% on September 30, 2027.
  2. Building costs about flat. Permit values per home were $404,000 in 2025 and $428,000 in 2026 so far. We don’t expect a big jump.
  3. More fourplexes than sixplexes. Six homes need a 50 ft lot and more paperwork. Most owners will keep building three or four.

Sources

Every outside figure traces to one of these pages, all opened on October 19, 2026. T-City’s own analysis uses the City of Vancouver open datasets. Rates and fee schedules change, so we recheck them for your lot during feasibility.

Common questions

Questions, Answered.

How much does it cost to build a multiplex in Vancouver?

About $1.7 million to $2.5 million for a fourplex on a 33 ft lot, before land and permit fees. That’s about $430,000 to $630,000 per home.

What is the cost per home to build a multiplex?

On Vancouver permits, the median construction value is $421,000 per home. Add charges, design, demolition and loan interest for the full cost.

How much are development charges on a Vancouver fourplex?

About $130,500 at rates from July 24, 2026: about $39,700 to the City and $90,800 to Metro Vancouver and TransLink.

Is a multiplex cheaper per home than a duplex?

About the same to build per home: $421,000 for a multiplex home against $450,000 for a duplex half. But multiplex homes are smaller, and each pays regional charges.

Do I need a disclosure statement to sell a fourplex?

No. You need one at five or more strata homes.