Protected trees and your build: Vancouver’s tree rules in 2026

Which trees are protected, when one can come out for a new home, what it costs, and how trees change a duplex or multiplex plan.

Rules and permits 6 min read By T-City Developments

A finished three-storey multi-unit home with grey and cedar cladding
Contents 12 sections
  1. What you need to know
  2. Which trees are protected
  3. When can a tree come out for a build
  4. What does the City need with your application
  5. How big is a tree protection barrier
  6. What do replacement trees cost
  7. The front-yard tree rule
  8. What if a tree is removed without a permit
  9. How do Burnaby and Surrey compare
  10. How we plan around trees
  11. Questions
  12. Sources

In Vancouver, any tree 20 cm or more across, measured 1.4 m above the ground, is protected. You need a permit to remove one, and for a new building it’s only allowed in set cases, such as the tree standing where the building has to go. Each removed tree is replaced with one large tree or two smaller ones, and fines run up to $10,000 per tree.

What you need to know

  • 20 cm: the trunk width that makes a tree protected, measured 1.4 m above the ground
  • $113 and $324: the permit fee for the first tree, and for each tree after that in 12 months
  • 1 or 2: replacement trees for each one removed, depending on their size
  • $1,000: cash instead of a replacement tree, only if your lot already has enough trees
  • Up to $10,000: the fine for each tree removed or damaged without a permit

Rules checked: October 2026. Sources: City of Vancouver Protection of Trees By-law No. 9958 (consolidated to December 9, 2025, fees effective January 1, 2026), City of Vancouver 2026 Schedule of Fees for Development and Building Permits. Bylaws change, so we confirm every figure against your specific lot during feasibility.

Which trees are protected?

Any tree with a trunk 20 cm (8 inches) or more across, measured 1.4 m above the ground. For a tree with several trunks, you add up the two or three biggest. Trees in a hedge and replacement trees are protected at any size.

For a new build, the rules reach past your lot line. The City wants to see every tree on your lot, every tree on a neighbour’s lot within 2 m of your line, and every street tree in front.

Rules checked: October 2026. Sources: City of Vancouver Protection of Trees By-law No. 9958 (consolidated to December 9, 2025, fees effective January 1, 2026). Bylaws change, so we confirm every figure against your specific lot during feasibility.

When can a tree come out for a build?

Only for set reasons. These are the ones that come up most on new homes:

  • It’s where the building has to go. The tree sits inside the building area on your permit, and moving a garage or shed can’t save it
  • It’s in the way of construction access, as decided by the City
  • Its roots are breaking a drain or sewer, confirmed by a certified plumber
  • It’s hazardous, damaged, dying or dead, confirmed by a certified arborist
  • It’s damaging property, like a roof or retaining wall, and pruning can’t fix it

On a sloping lot, an engineer must also confirm that taking the tree out won’t loosen the soil.

Rules checked: October 2026. Sources: City of Vancouver Protection of Trees By-law No. 9958 (consolidated to December 9, 2025, fees effective January 1, 2026). Bylaws change, so we confirm every figure against your specific lot during feasibility.

What does the City need with your application?

With a development or building permit, you send two reports about the trees:

  • A land survey showing each tree on your lot, within 2 m on the neighbour’s side, and on the street, with its drip line (the edge of its branches)
  • An arborist’s report on each tree’s health, how the build affects it, and how to protect it. The arborist also agrees to check the site during construction and after

Plan for both early. They come before design is final, because a protected tree can move the whole building. See how long a build takes.

Rules checked: October 2026. Sources: City of Vancouver Protection of Trees By-law No. 9958 (consolidated to December 9, 2025, fees effective January 1, 2026). Bylaws change, so we confirm every figure against your specific lot during feasibility.

How big is a tree protection barrier?

Before any demolition or digging, each tree you keep needs a fence around it. It must be at least 1.2 m high, usually snow fencing on stakes. The bigger the trunk, the farther out the fence goes:

A 60 cm tree needs a fence 3.6 m out from its trunk Minimum distance from the trunk to the protection barrier, by trunk diameter measured 1.4 m above the ground
  • Common sizes on older Vancouver lots
  1. 20 cm trunk : 1.2 m
  2. 30 cm trunk : 1.8 m
  3. 40 cm trunk : 2.4 m
  4. 50 cm trunk : 3.0 m
  5. 60 cm trunk : 3.6 m
  6. 75 cm trunk : 4.5 m
  7. 90 cm trunk : 5.0 m
  8. 100 cm trunk : 6.0 m

City of Vancouver Protection of Trees By-law No. 9958, Schedule A (consolidated to December 9, 2025). Selected sizes; the schedule lists every 5 cm from 20 to 60 cm

Chart: T-City Developments · tcitydevelopments.com

The City inspects the fences before it issues the demolition or building permit. For a neighbour’s tree near your line, the fence reaches at least 2 m into your lot. On a 33 ft lot, that can take a real bite out of where you can dig and park equipment.

Rules checked: October 2026. Sources: City of Vancouver Protection of Trees By-law No. 9958 (consolidated to December 9, 2025, fees effective January 1, 2026). Bylaws change, so we confirm every figure against your specific lot during feasibility.

What do replacement trees cost?

For each tree you remove, you plant one large replacement tree or two smaller ones, before you move in. You also leave a deposit until the City approves them:

Vancouver tree permit costs (2026)
ItemCost
Permit, first tree in 12 months$113
Permit, each tree after that$324
Deposit per replacement tree$500, or $750 for a tree 8 cm or more
Cash instead of planting$1,000 per tree, only if the lot already meets its tree minimum

The tree minimum depends on lot size. A typical 33 × 122 ft lot is about 374 m², which needs 3 trees, and a 50 × 122 ft lot needs 5. Replacement trees must be at least 1.5 m from a house and 2.5 m from other trees.

Rules checked: October 2026. Sources: City of Vancouver Protection of Trees By-law No. 9958 (consolidated to December 9, 2025, fees effective January 1, 2026), City of Vancouver 2026 Schedule of Fees for Development and Building Permits. Bylaws change, so we confirm every figure against your specific lot during feasibility.

The front-yard tree rule

This one catches people out. In Vancouver’s R1-1 zone, a new multiplex, a duplex with a suite, a house with a suite, or a laneway house needs trees in the front yard:

  • Lot under 15.1 m (49.5 ft) wide: keep one front-yard tree, or plant one
  • Lot 15.1 m or wider: keep two, or plant enough to make two

A kept tree must be 20 cm or more across. If your lot has no lane, the City can relax this rule. See the duplex rules for the rest of R1-1.

Rules checked: October 2026. Sources: Vancouver R1-1 District Schedule, section 2.2.1 (June 2026). Bylaws change, so we confirm every figure against your specific lot during feasibility.

What if a tree is removed without a permit?

Each tree counts as its own offence. The fine is $500 to $10,000 per tree, and $250 to $10,000 for each day a breach continues. The City can also make you plant replacement trees and stop work on the site.

Rules checked: October 2026. Sources: City of Vancouver Protection of Trees By-law No. 9958 (consolidated to December 9, 2025, fees effective January 1, 2026). Bylaws change, so we confirm every figure against your specific lot during feasibility.

How do Burnaby and Surrey compare?

Protected trees in three cities (2026)
ItemVancouverBurnabySurrey
Protected size20 cm20 cm on a development site. 30 cm conifer or 45 cm leafy tree otherwise30 cm, plus some species at any size
Replacement trees1 large or 2 smaller1 to 3, by the size of the tree removedUp to 2 per tree, set by the arborist report
Permit fee$113, then $324 a treeSet in the fees bylaw$108 plus $42 a tree
Cash instead$1,000 a treeTo the Civic Tree Reserve Fund$550 a tree
Deposit on kept treesNone set in the bylawReplacement security$3,000 per kept tree on a development
Top fine$10,000 per treeSet in the bylaw$20,000

Rules differ a lot by city, and so do the deposits. We check your city’s tree rules during the lot feasibility study, before design.

Rules checked: October 2026. Sources: City of Burnaby: Tree removal and replacement, City of Surrey: Removing trees, City of Surrey: Trees and landscape, land development requirements. Bylaws change, so we confirm every figure against your specific lot during feasibility.

How we plan around trees

Trees are easiest to deal with at the start. A good plan does three things:

  • Finds the trees first. The survey and arborist come before the design, not after
  • Shapes the building around the best trees. A courtyard or a shifted garage can save a tree and its permit fees
  • Prices the rest. Barriers, replacement trees and deposits go in the budget from day one

If a big tree sits right where the building has to go, that’s usually a valid reason to remove it. If it sits in the backyard, it may decide where a laneway house or rear building goes. See duplex floor plans on a 33 ft lot.

Sources

Every outside figure traces to one of these pages, all opened on October 29, 2026. Rates and fee schedules change, so we recheck them for your lot during feasibility.

Common questions

Questions, Answered.

What size tree is protected in Vancouver?

Any tree with a trunk 20 cm or more across, measured 1.4 m above the ground. Hedge trees and replacement trees are protected at any size.

How much is a tree removal permit in Vancouver?

$113 for the first tree in a 12-month period, and $324 for each tree after that (2026 fees).

Can I remove a tree to build a duplex in Vancouver?

Only in set cases, such as the tree standing inside the building area on your permit when it can’t be saved by moving an accessory building. You must replace it.

Do I need an arborist report to build in Vancouver?

Yes. A development or building permit needs an arborist’s report and a land survey showing the trees on and near your lot.

What is the fine for cutting down a tree in Vancouver?

$500 to $10,000 per tree, and each tree is a separate offence.

Do I need front-yard trees for a multiplex in Vancouver?

Yes. In R1-1, keep or plant one front-yard tree on a lot under 15.1 m wide, and two on a wider lot.