With a fixed price contract, you agree on one price for the job, and the builder carries the risk if costs rise. With cost plus, you pay what the work actually costs, plus a fee, and you carry that risk. Fixed price gives you certainty but usually includes a cushion for the unknown. Cost plus can cost less if things go well, and more if they don’t. In Vancouver, build prices rose 15% in 2022 alone, then just 0.6% in the year to July 2026.
What we found
-
15.5%
Rise in what contractors charged to build a new Vancouver house in 2022, after 11.5% in 2021. Statistics Canada’s construction price index, yearly average.
-
0.6%
Rise in Vancouver build prices from July 2025 to July 2026, the smallest in years.
-
10%
Of every payment to a BC builder is held back under the Builders Lien Act, whichever contract you choose, until 55 days after the job is substantially done.
- Over 10% in a year
T-City calculation from Statistics Canada table 18-10-0289-01, building construction price index, single-detached house, Vancouver: change in the yearly average. July 2025 to July 2026: 0.6%
What is a fixed price contract?
One price for the whole job, agreed before work starts. If materials or labour cost more than planned, the builder absorbs it. If you change the design, you pay for the change through a change order.
- Good for: owners who need a firm budget, like for a construction loan
- Watch for: a cushion built into the price, and “allowances” for things like cabinets or flooring that can run over
What is a cost plus contract?
You pay the actual cost of labour and materials, plus the builder’s fee. The fee is either a percentage of the cost or a fixed amount. You see every invoice.
- Good for: custom homes where the design is still changing, or owners who want to see every cost
- Watch for: a percentage fee, which grows as costs grow. A fixed fee doesn’t
Fixed price vs cost plus: side by side
| Item | Fixed price | Cost plus |
|---|---|---|
| Who pays if costs rise | The builder | You |
| Price certainty | High | Low |
| What you see | The price and any change orders | Every invoice |
| Design changes | Change orders, priced one by one | Easier, but every change adds cost |
| Best when | Plans are final | Plans are still evolving |
Some contracts mix the two. A cost plus deal with a guaranteed maximum price caps what you pay, and you may share any savings below the cap.
Why it matters more in Vancouver
Builds here are big and slow. A new house permit declared a median of about $1 million in 2025 and 2026, and building takes a year or more after the permit. Over 2021 and 2022, prices rose about 29%. On a cost plus job, that rise landed on the owner. On a fixed price job signed before it, it landed on the builder. Today prices are flat, so the cushion in a fixed price is worth less. See what a permit value really tells you.
What to ask any builder
- Which contract do you offer, and why?
- What’s in the allowances, and what happens if we go over?
- How are change orders priced? Get it in writing before work starts
- Is your fee a percentage or a fixed amount? (For cost plus)
- Is the home enrolled for 2-5-10 warranty? New homes from a licensed BC builder need it, with few exceptions
- How do you handle the 10% lien holdback? It’s the law on every job
Which should you choose?
- Plans final and a lender involved? Fixed price is usually simpler
- Custom design still changing? Cost plus with a fixed fee, or a guaranteed maximum price
- Either way, start with a real budget. See our house and duplex cost guides, or get a lot feasibility study